Deposit and Progress Invoices: Billing in Stages

In this guide
- The four kinds of staged billing
- Staged billing from the client’s side
- Why bill in stages
- How much to ask for
- Fitting staged billing into your quote
- The documents, in order
- Choosing the trigger for each payment
- Worked example 1: a design project
- Worked example 2: a building or renovation project
- Worked example 3: a product made to order
- Worked example 4: a retainer
- Variations, extras and change orders
- Refunds and cancellations
- Deposits that are not deposits: holding fees, security and reservations
- Tax and deposits
- Recording staged billing in your books
- Deposit invoices versus pro forma invoices
- Wording that works
- Emails to send with staged invoices
- Questions clients ask about deposits
- Staged billing in different kinds of business
- When the deposit does not arrive
- Bookings, events and fixed dates
- Keeping the client informed as the project moves
- Mistakes to avoid
- A staged billing checklist
- Create your staged invoices
Billing the whole of a large job at the end is a quiet way to take on a great deal of risk. You pay for the materials, the time and the stress, and you wait to find out whether the client pays. Deposits and progress invoices solve that by spreading the payment across the life of the project, so the money arrives roughly as the work happens.
This guide explains each type of staged invoice, how much to ask for, how to word the documents, what the final invoice should show and how to handle refunds, tax and changes. There are worked examples for services, construction-style projects and products. To make the documents, use the free invoice generator.
Quick answer: Ask for a deposit of around 25 to 50 percent before you start, bill further stages as milestones are reached, and make the final invoice show the full price, the amounts already paid and the balance due. Put all of it in the quote or contract first.
The four kinds of staged billing
People use the words loosely, so it helps to separate them. Each solves a slightly different problem.
| Type | What it is | When it is issued | Typical use |
|---|---|---|---|
| Deposit | A first payment before work starts | At acceptance of the quote | Almost any project |
| Progress invoice | A bill for work completed so far | At agreed intervals or percentages | Long or large projects |
| Milestone invoice | A bill triggered by a delivered milestone | When the milestone is approved | Phased projects |
| Retainer | A fixed regular fee for ongoing work | Usually monthly in advance | Ongoing support |
| Final invoice | The balance after earlier payments | On completion | Every staged project |
A single project often uses several of these together: a deposit at the start, milestone invoices in the middle and a final invoice at the end.
Staged billing from the client’s side
It helps to see staged billing through the client’s eyes, because clients are the ones who have to agree to it. A client considering a large project is weighing risk too: will the work be delivered, on time, and to the standard promised? Staged payments answer that worry as well as yours.
| Client concern | How staged billing helps |
|---|---|
| “What if they take the money and disappear?” | They pay only in step with visible progress |
| “What if the work is poor?” | They can pause or stop at a checkpoint |
| “How do we budget?” | Payments are spread and scheduled |
| “Who approves what?” | Each milestone is a clear approval point |
| “How do we know the price is fair?” | Each stage is itemised against the quote |
When you propose a deposit, frame it as a shared protection, not a demand. A sentence such as “I take a 40% deposit to reserve your slot and cover early costs, and then bill by milestone so you only pay for work you have seen” tends to be well received. Most business clients are used to the idea, and many have their own approval processes built around stage payments.
Why bill in stages
| Benefit | What it gives you |
|---|---|
| Cash flow | Money arrives while the work is under way |
| Reduced risk | You are never owed a large sum for long |
| Commitment | The client has put money in and is invested in the project |
| Smaller invoices | Easier for clients to approve and pay |
| Natural checkpoints | Approval at each stage prevents surprises |
| Fairness | The client pays for progress they can see |
For the client, staged billing also has advantages: they can see value before paying everything and they can stop if things are going badly. Presented that way, it is easy to agree.
How much to ask for
There is no fixed rule. The right amount depends on your costs, the size of the project and the relationship.
| Project | Common structure | Reasoning |
|---|---|---|
| Small job, under a week | 50% deposit, 50% on delivery, or 100% upfront | Short and simple |
| Medium project, a few weeks | 30 to 50% deposit, balance on delivery | Covers your early costs |
| Large project, months | 20 to 30% deposit, then milestones, final 10 to 20% on completion | Spreads risk |
| Product made to order | 50% to order, balance before shipping | Covers materials |
| Ongoing service | Monthly in advance | Predictable income |
| New or unknown client | Higher deposit | Reduces risk |
| Trusted repeat client | Lower deposit or terms | Reflects the relationship |
A useful test is to ask what you would lose if the client disappeared after paying only the deposit. The deposit should at least cover your direct costs and a fair share of your time for the work you would have started. If it does not, raise it.
Fitting staged billing into your quote
The cleanest way to introduce staged billing is to build it into the quote, so the client agrees to it at the same time as the price. A payment schedule section can be short.
| Stage | Trigger | Share | Amount |
|---|---|---|---|
| Deposit | Acceptance of this quote | 30% | $3,600.00 |
| Milestone 1 | Design approved | 30% | $3,600.00 |
| Milestone 2 | Build complete, ready for review | 30% | $3,600.00 |
| Final | Launch and handover | 10% | $1,200.00 |
| Total | 100% | $12,000.00 |
Add a line for what happens if a milestone is delayed by the client, such as “If approval is not received within 10 working days, the milestone invoice will be issued automatically.” This protects you from a project that sits half-finished while payment waits. Add another for what happens at the end: “The final payment is due on handover.” The quote generator lets you list the schedule with the terms.
The documents, in order
A staged project creates a short chain of documents. Keeping each one clearly labelled, numbered and linked to the quote prevents confusion.
| Step | Document | What it does |
|---|---|---|
| 1 | Quote | States scope, total price and payment schedule |
| 2 | Acceptance | Written agreement from the client |
| 3 | Deposit invoice | Requests the first payment |
| 4 | Receipt | Confirms the deposit was received |
| 5 | Progress or milestone invoices | Bill each stage |
| 6 | Final invoice | Shows full value, payments received and balance |
| 7 | Receipt | Confirms the final payment |
The quote generator can state the schedule up front, and the receipt generator confirms each payment.
The deposit invoice
A deposit invoice looks like any other invoice, with a few specific features.
| Element | Example |
|---|---|
| Title | Invoice, or “Deposit invoice” |
| Description | “50% deposit for kitchen renovation, as per quote Q-0031” |
| Reference to the quote | Quote number and date |
| Amount | A fixed sum or percentage with the total shown |
| Due date | Before work starts, such as “Due on acceptance” |
| What it secures | “Reserves your start date of 2 December” |
| Policy | “Deposit is non-refundable after materials are ordered” |
Say clearly what the deposit is for and what happens to it. It reads as professional, and it prevents disagreement if the project is cancelled.
Progress and milestone invoices
Progress invoices bill for work completed. There are two common ways to define “completed”.
| Method | How it works | Good for |
|---|---|---|
| Milestones | Each named deliverable triggers a payment | Projects with clear phases |
| Percentage complete | A share of the total, agreed or measured | Construction and long builds |
| Time and materials | Hours and costs to date | Uncertain or evolving scope |
| Fixed calendar dates | A set amount on set dates | Long projects with a steady pace |
Whichever you use, say in the quote how stages are measured and who confirms them. An invoice for “milestone 2: design approved” is straightforward when the milestone was defined at the start. An invoice for “about 60% done” invites debate.
The final invoice
The final invoice should give the client a complete picture: the whole price, what has been paid and what remains. This is the most important design point in staged billing, because it prevents confusion and double payment.
| Line | Amount |
|---|---|
| Project total (quote Q-0031) | $12,000.00 |
| Less deposit paid (invoice 0051, 2 Dec) | -$3,600.00 |
| Less milestone 2 paid (invoice 0056, 20 Dec) | -$3,600.00 |
| Balance due | $4,800.00 |
Notice that every earlier payment is listed with its invoice number and date. A client or an accountant can reconcile the final figure at a glance.

Choosing the trigger for each payment
The trigger is the heart of any schedule. A good trigger is objective, visible to both sides and hard to dispute. A poor one invites argument.
| Weak trigger | Why it fails | Better trigger |
|---|---|---|
| “When about half done” | Subjective | “When the first draft is delivered” |
| “When the client is happy” | Open-ended | “When the client approves in writing, or after 10 working days without comments” |
| “At the end of the month” | Unrelated to the work | “On delivery of milestone 2” |
| “When we have time” | No commitment | A specific date or event |
| “On completion” | Might be disputed | “On handover of the final files” |
A deemed-approval clause is especially useful. If the client has not responded within a set period, the milestone is treated as approved. It stops one slow reply from freezing both the work and the payments, and it is easy to word fairly.
Worked example 1: a design project
A freelance designer agrees a $6,000.00 brand identity project: 40% deposit, 30% on concept approval and 30% on final delivery.
| Invoice | Trigger | Amount | Paid |
|---|---|---|---|
| 0061 Deposit | Quote accepted | $2,400.00 | 3 Nov |
| 0064 Concept approved | Client approves concept | $1,800.00 | 21 Nov |
| 0068 Final | Files delivered | $1,800.00 | 12 Dec |
| Total | $6,000.00 |
Each invoice references the quote and states the milestone. The final invoice lists the previous two as “paid” so the client sees $6,000.00 in total. In this case, the final invoice can also state “Paid in full” once the receipt is issued.
Worked example 2: a building or renovation project
Construction and renovation work often uses staged billing with a held-back retention.
| Item | Detail |
|---|---|
| Contract price | $40,000.00 |
| Deposit | 10%: $4,000.00 |
| Progress payments | Monthly, by percentage complete |
| Retention | 5% held until completion and defect period ends |
Here is how three monthly progress invoices might look.
| Month | Work complete to date | Value to date | Less retention 5% | Less previously paid | This invoice |
|---|---|---|---|---|---|
| Month 1 | 20% | $8,000.00 | -$400.00 | -$4,000.00 (deposit) | $3,600.00 |
| Month 2 | 55% | $22,000.00 | -$1,100.00 | -$7,600.00 | $13,300.00 |
| Month 3 | 90% | $36,000.00 | -$1,800.00 | -$20,900.00 | $13,300.00 |
Check the Month 2 line: value to date of $22,000.00 less retention of $1,100.00 is $20,900.00 owed in total so far. Previously paid is $7,600.00 ($4,000.00 deposit plus $3,600.00 from month 1). The invoice is $20,900.00 minus $7,600.00, which is $13,300.00. Month 3: $36,000.00 minus $1,800.00 is $34,200.00; previously paid $7,600.00 plus $13,300.00 is $20,900.00; invoice $13,300.00.
At practical completion, the final invoice bills the remaining value, and the retention is released at the end of the defects period under the contract.
Worked example 3: a product made to order
A furniture maker agrees to build a dining table for $3,200.00, with 50% to start and the balance before delivery.
| Stage | Document | Amount | Notes |
|---|---|---|---|
| Order | Deposit invoice 0072 | $1,600.00 | Covers timber and a start date |
| Completion | Final invoice 0075 | $1,600.00 | Due before delivery |
| Delivery | Receipt | Paid in full | Issued when delivered |
On the final invoice, the maker shows the table price, the deposit paid and the balance. If tax applies, it is calculated on the full price and shown on the final invoice, with the deposit deducted from the total including tax.
Worked example 4: a retainer
A consultant provides up to 10 hours of advice each month for $1,500.00, invoiced on the first of the month.
| Month | Invoice | Amount | Notes |
|---|---|---|---|
| January | 0081 | $1,500.00 | Up to 10 hours, January |
| February | 0085 | $1,500.00 | Up to 10 hours, February |
| March | 0089 | $1,500.00 + $150.00 | Extra 1 hour at $150.00 |
Retainer invoices should state the period covered, what is included and what happens to unused hours. If hours do not roll over, say so in the agreement and on the invoice. A retainer is normally invoiced in advance, which makes cash flow predictable.
Variations, extras and change orders
Staged projects change as they go. How you handle changes should be part of the agreement, because each change affects the schedule and the amount still to be billed.
| Change | How to handle it | On the invoices |
|---|---|---|
| Small addition | Confirm in writing, with price | A separate line on the next invoice |
| Larger addition | Issue a variation or change order | A new milestone or adjusted total |
| Work removed | Agree the reduction in writing | Credit on the next invoice or final invoice |
| Timeline change | Agree new dates | Adjust milestone dates |
| Client-supplied delay | Apply the deemed-approval or delay clause | Issue the milestone invoice as per the agreement |
A change order can be a short document: a description, the price, the effect on the timeline and a space for the client to approve it. Keep it with the quote and refer to it on the invoice, such as “Includes change order CO-02, approved 2 December.” The final invoice then shows the original price plus approved changes, with no surprises.
Refunds and cancellations
A deposit raises the question of what happens if the project does not go ahead. Settling it in advance is far better than arguing about it later.
| Situation | Typical treatment | What to document |
|---|---|---|
| Client cancels before work starts | Full refund or small admin fee | Quote terms |
| Client cancels after work started | Keep an amount covering work done and costs | Record of work and costs |
| You cancel | Refund in full | Notice and refund |
| Project paused | Hold deposit, set a restart date | Written agreement |
| Materials already bought | Non-refundable to that extent | Receipts |
| Reserved time or a start date | A reservation element can be non-refundable | Wording on the quote |
Credit notes for refunds
If you refund part or all of a deposit, record it with a credit note that references the deposit invoice, then pay the refund. The credit note generator produces it, and what is a credit note explains the process and the tax effects.
Consumer protection
If your client is a consumer, local rules may give them cancellation or refund rights that cannot be removed by your terms. Check what applies to you, particularly for distance sales, services at the customer’s home and large contracts.
Deposits that are not deposits: holding fees, security and reservations
The word deposit covers several different arrangements, and they are treated differently. It helps to know which one you are using.
| Type | What it is | Typical treatment |
|---|---|---|
| Part payment or advance | A first instalment of the price | Counts towards the price, deducted at the end |
| Booking or reservation fee | Pays to hold a date or slot | Often non-refundable, may or may not be credited |
| Security deposit | Held against damage or non-performance | Returned if conditions are met |
| Holding deposit | Reserves goods or a place for a limited time | Credited if the purchase goes ahead, otherwise governed by terms |
| Retention | Part of progress payments held back by the client | Released at completion or end of a defects period |
Be precise about which you mean on the invoice and in the quote. “Booking fee, non-refundable, credited against the final invoice” and “Security deposit, refundable within 14 days of completion” are very different promises, and calling both a “deposit” is a common cause of disputes.
Tax and deposits
The tax treatment of advance payments depends on where you are and what you sell. Some general points apply in many places.
| Question | General position |
|---|---|
| Is tax due when I receive a deposit? | In many VAT and GST systems, yes: tax is due on an advance when invoiced or received |
| Is a deposit income when received? | Depends on your accounting method and local rules |
| Do I show tax on the deposit invoice? | Often yes, calculated on the deposit amount |
| How is it shown on the final invoice? | Full value with tax, less deposit including its tax |
| What if the sale does not happen? | A credit note reverses the tax |
| Are there special rules for exports? | Often, so check before invoicing deposits for overseas sales |
Here is how the arithmetic can look with tax at 8% on a $5,000.00 job and a 40% deposit.
| Document | Net | Tax at 8% | Total |
|---|---|---|---|
| Deposit invoice (40%) | $2,000.00 | $160.00 | $2,160.00 |
| Final invoice, full value | $5,000.00 | $400.00 | $5,400.00 |
| Less deposit paid | -$2,000.00 | -$160.00 | -$2,160.00 |
| Balance due | $3,000.00 | $240.00 | $3,240.00 |
If you are unsure whether tax is due on deposits in your situation, ask an accountant or your tax authority. For general guidance on showing tax, see sales tax on invoices. For US contractors, see the 1099 invoice guide.
Recording staged billing in your books
Staged billing complicates the books a little, because money arrives before the work is complete. A simple routine keeps it tidy.
| Event | How to record it |
|---|---|
| Deposit invoice issued | Record the invoice as a receivable, labelled as a deposit or advance |
| Deposit received | Record the payment against the invoice; the amount is usually shown as a customer deposit until the work is delivered |
| Milestone invoice issued | Record as a sale for the completed stage, according to your accounting method |
| Final invoice issued | Show full value; apply earlier payments |
| Refund | Record a credit note and the refund payment |
| Retention held | Track as a separate receivable until released |
Your accountant can advise on the right treatment for your accounting method and tax. The main practical point is to keep one list of every staged project showing the total price, the amounts invoiced, the amounts paid and the balance. A table like this is enough.
| Project | Total | Invoiced | Paid | Outstanding | Not yet invoiced |
|---|---|---|---|---|---|
| Northline rebrand | $12,000.00 | $7,200.00 | $7,200.00 | $0.00 | $4,800.00 |
| Oak kitchen | $40,000.00 | $21,000.00 | $13,300.00 | $7,700.00 | $19,000.00 |
| Lee table | $3,200.00 | $1,600.00 | $1,600.00 | $0.00 | $1,600.00 |
Deposit invoices versus pro forma invoices
The two are often confused. A pro forma invoice is a preliminary document that is not a request for payment in its own right, though buyers may pay an advance against it. A deposit invoice is a real invoice that asks for a part payment. In many tax systems a deposit invoice is a proper invoice that has tax consequences, while a pro forma generally does not. For more, read pro forma vs commercial invoice.
| Deposit invoice | Pro forma invoice | |
|---|---|---|
| Status | A real invoice | A preliminary document |
| Purpose | Collect a part payment | Preview a sale, support finance or customs |
| Recorded as a sale | Often, as an advance | No |
| Tax | Often applies | Usually not |
| Common in | Domestic projects and services | International trade |
Wording that works
Clear wording prevents disputes. These examples can be adapted.
| Where | Wording |
|---|---|
| Quote | “A 40% deposit of $2,400.00 is due on acceptance to reserve your start date.” |
| Deposit invoice | “Deposit for brand identity project, as per quote Q-0031. The deposit will be deducted from the final invoice.” |
| Cancellation | “Deposits are refundable in full if you cancel before work begins. After that, they cover work completed and costs incurred.” |
| Milestone invoice | “Milestone 2 of 3: concept approved on 21 November.” |
| Final invoice | “Project total $6,000.00, less payments received $4,200.00. Balance due $1,800.00.” |
| Retainer | “Monthly retainer for December: up to 10 hours of advisory support.” |
Emails to send with staged invoices
Asking for a deposit
Subject: Quote Q-0031 and deposit invoice
Hi Sam,
Thank you for confirming the project. Attached are the final quote and the deposit invoice (0061) for 40%, $2,400.00. Once it is paid I will reserve your start date of 2 December. The deposit is deducted from the final invoice.
Best, Maya
Milestone reached
Subject: Invoice 0064: concept approved
Hi Sam,
Thank you for approving the concept. As agreed, invoice 0064 for the second payment of $1,800.00 is attached, due 5 December. I will start on the final artwork as soon as it is paid, or tomorrow if you prefer to pay on completion.
Best, Maya
Questions clients ask about deposits
Clients new to staged payments often have the same few questions. Having ready answers makes the conversation smooth.
| Question | A clear answer |
|---|---|
| “Why do you need a deposit?” | “It covers my early costs and reserves your place in my schedule. It is deducted from the final invoice.” |
| “Is it refundable?” | “Yes, in full, if you cancel before work starts. After that it covers work done and costs incurred.” |
| “Can we pay in two parts?” | “Yes. I can do 50% now and 50% on delivery.” |
| “What happens if you are late?” | “The schedule sets dates for each milestone, and we can agree what happens if either side is delayed.” |
| “Why not pay at the end?” | “For projects this size I bill in stages. It keeps the invoices smaller for you and the risk fair for both of us.” |
| “Will tax be added to the deposit?” | “If tax applies to the project, it is included on each invoice, and the final invoice shows the total with the deposit deducted.” |
Answering in plain language, without defensiveness, is usually all it takes. A client who understands why you bill this way is more likely to respect the schedule.
Staged billing in different kinds of business
The idea is the same everywhere, but the details differ with the trade. These patterns are common starting points, to be adjusted to your own costs and risk.
| Business | Typical structure | Triggers | Notes |
|---|---|---|---|
| Web designer or developer | 30 to 50% deposit, milestones, final on launch | Design approval, build complete, launch | Add a clause for client delays |
| Writer or content studio | 25 to 50% upfront for large batches, rest on delivery | Delivery of batches | Per-piece invoices work for ongoing work |
| Photographer | Booking fee or 50% deposit, balance before delivery of images | Shoot date, delivery | Deposits often reserve the date and are non-refundable |
| Builder or renovator | 10 to 20% deposit, monthly progress invoices, retention | Percentage complete, certified valuations | Retention and defects period matter |
| Event planner | Deposit at booking, instalments, balance before the event | Calendar dates | Cancellation schedule is important |
| Consultant | Monthly retainer or milestone fees | Month start, deliverables | Time caps prevent open-ended work |
| Manufacturer or maker | 50% on order, balance before shipping | Order, completion | Materials are the main risk |
| Translator or editor | Deposit on large jobs, rest on delivery | Delivery | Word count caps help |
Whatever your trade, ask what the largest cost you carry before being paid is, and make sure the first payment covers it.
When the deposit does not arrive
Sometimes a client accepts the quote, but the deposit invoice sits unpaid. How you respond matters, because starting work without it removes your leverage.
- Do not start. The deposit is the condition for beginning, as agreed.
- Send a friendly reminder the day after the due date, mentioning that the start date is reserved only once the deposit is received.
- Offer help. Ask if there is a PO number or a payment method that would make it easier.
- Set a deadline for the reservation. “I can hold the 2 December slot until Friday. After that, the next available start is 16 December.”
- Release the slot if nothing happens, and tell the client in writing.
This keeps your schedule full of paying work and shows professionalism without any hostility. Most clients who delay a deposit are simply slow, and a clear deadline brings them round.
Bookings, events and fixed dates
When you are reserving a particular date, such as an event, a shoot or a delivery slot, the deposit has a second job: it compensates you for the work you turn away. This is why booking deposits are so often non-refundable.
| Element | What to say |
|---|---|
| What the deposit reserves | “This deposit reserves 14 March 2027 exclusively for your event.” |
| What happens if the client cancels | A cancellation schedule, such as “more than 60 days before: deposit retained, balance not due; 60 to 30 days: 50% of the total; under 30 days: 100%.” |
| What happens if you cancel | Full refund and, if appropriate, help finding a replacement |
| Rescheduling | “One free date change if requested at least 30 days in advance; later changes are subject to availability.” |
| Balance due date | “Final balance due 14 days before the event.” |
A cancellation schedule that rises as the date approaches is fair and easy to explain: the closer the date, the harder it is to fill the slot with someone else. Put it in the quote, point to it in the deposit invoice and keep a signed or emailed acceptance.
Keeping the client informed as the project moves
Staged billing works best when clients are never surprised by an invoice. A small amount of communication at each stage makes payment almost automatic.
| Moment | What to send | Why |
|---|---|---|
| Quote accepted | A summary of the schedule and the first invoice | Starts clearly |
| Before a milestone | A note that the next stage is nearly ready for review | Prepares the client to approve |
| Milestone delivered | The deliverable and a request for approval | Triggers the invoice |
| Approval received | The milestone invoice, quoting the approval | Makes payment easy |
| Payment received | A receipt and a short progress update | Keeps goodwill high |
| Final delivery | A handover summary with the final invoice | Closes cleanly |
A short progress update with each payment shows the client what their money has bought. It reinforces the value, and it turns each invoice into a natural checkpoint instead of an interruption. Over a long project, this rhythm is what keeps the relationship comfortable for both sides.
Mistakes to avoid
| Mistake | Why it hurts | Fix |
|---|---|---|
| No written payment schedule | Disputes about what is due | Put it in the quote |
| Unclear deposit refund rules | Arguments on cancellation | State the policy |
| Final invoice does not show earlier payments | Double payment or confusion | List each payment with number and date |
| Progress billed on vague percentages | Disagreement about progress | Define milestones or measure |
| Mixing deposit and final invoice numbers | Messy records | Number each invoice separately |
| Starting before the deposit arrives | You carry the risk | Begin on receipt |
| Ignoring tax on advances | Reporting errors | Check the rules |
| Forgetting receipts | Gaps in records | Issue one for each payment |
A staged billing checklist
| Check | Done |
|---|---|
| Schedule agreed in the quote or contract | |
| Deposit amount and due date stated | |
| Refund and cancellation policy written | |
| Milestones or measures defined | |
| Each invoice has its own number and references the quote | |
| Receipts issued for each payment | |
| Final invoice lists all earlier payments | |
| Tax treated consistently | |
| Changes confirmed in writing and billed separately | |
| All documents filed together |
Create your staged invoices
The invoice generator lets you add the project total, subtract a deposit or earlier payments, show tax and save a clean PDF in your browser. Use the same tool for the deposit invoice, each progress invoice and the final one, and the receipt generator to confirm each payment. For more ways to bring cash in sooner, read how to get paid faster.
This guide is general information and is not legal, tax or accounting advice. Contract, consumer and tax rules vary, so check what applies to you.
Frequently asked questions
What is a deposit invoice?
A deposit invoice asks a client to pay part of the total price before work begins. It is usually a fixed amount or a percentage of the quoted price, and it is deducted from the final invoice.
How much deposit should I ask for?
Between 25 and 50 percent is typical for projects. Smaller jobs sometimes ask for 100 percent upfront, while large or long projects use a smaller deposit followed by progress payments.
What is a progress invoice?
A progress invoice bills for the part of a project that has been completed so far, either by percentage complete or by milestone, so you are paid in stages instead of at the end.
Is a deposit refundable?
It depends on what was agreed. A deposit is commonly refundable if the work has not started, and partly or fully non-refundable if you have incurred costs or reserved time. State the policy in the quote or contract.
How do I show a deposit on the final invoice?
Show the full project value, then a line for the deposit already paid with its invoice number and date as a deduction, and finally the balance due.
Do I charge tax on a deposit?
In many tax systems, tax is due when you receive an advance payment or issue an invoice, even before delivery. Rules differ by country and by type of sale, so check with your tax authority or adviser.
What is a retainer invoice?
A retainer invoice bills a regular fixed amount, usually monthly, for an agreed scope of ongoing work or availability. It is normally invoiced in advance.
What is retention in progress billing?
Retention is a percentage of each progress payment, often 5 to 10 percent in construction, that the client holds back until the work is complete or defects are corrected.